UPDATE from Jon Shadduck our project engineer!
ELECTRICAL - All electrical is complete. I have a few clean up electrical items that should take about 15 minutes before we startup. A great big THANK YOU to Darryl Simmons, Roger Gleber, Jeff Kenee, and Darryl’s co-worker (I can’t remember his name). These folks saved a TON of money for camp! Based on our proposals, I would estimate that they saved camp about $4-6000. THANKS!!
OLD SYSTEM - Loana, our contractor, has cut over the sewer drains into our new system, covered everything up, and laid down seed and straw. Our old system is GONE! We can’t use the facilities until we get DNR certification.
STARTUP – The equipment vendor, Flo-systems, will come out and set up all their equipment and give Bill and I a hands-on training lesson for the system.
ELECTRICAL - All electrical is complete. I have a few clean up electrical items that should take about 15 minutes before we startup. A great big THANK YOU to Darryl Simmons, Roger Gleber, Jeff Kenee, and Darryl’s co-worker (I can’t remember his name). These folks saved a TON of money for camp! Based on our proposals, I would estimate that they saved camp about $4-6000. THANKS!!
OLD SYSTEM - Loana, our contractor, has cut over the sewer drains into our new system, covered everything up, and laid down seed and straw. Our old system is GONE! We can’t use the facilities until we get DNR certification.
STARTUP – The equipment vendor, Flo-systems, will come out and set up all their equipment and give Bill and I a hands-on training lesson for the system.
INSPECTION - Once startup is complete, we will schedule the DNR and our engineer to come out for final inspection. I have been in contact with our engineers and the DNR. We hope to have all certifications done by May 1 in time for the retreat May 2-3, and it looks good at this time. I will keep everyone posted.
No comments:
Post a Comment